- Sector
- Transport infrastructure
- Project type
- Refurbishment
- Services provided
- Site survey
- Planning advice
- Design
- Product / system manufacture
- Product / system supply
- Installation
- Project location
- Wales
- Client
- Welsh Government
- Consultant
- Jacobs
- Contractor
- Alun Griffiths (Contractors) Ltd
- Products used
- Textomur
Overview
Phi Group's Textomur reinforced soil slope system has been used to great effect on a major highways scheme in West Wales. Principal Contractor, Alun Griffiths (Contractors) Ltd, appointed Phi Group to supply and install two Textomur reinforced soil slopes, whilst also providing design input for Jacobs, the scheme engineers.
Project
The A40 between St Clears and Haverfordwest is mainly a single carriageway. Works to the existing road between Llanddewi Velfrey and Redstone Cross will improve safety, and incorporate new cycling and walking routes.
Scheme engineer Jacobs contacted Phi Group at an early stage as the scheme required existing levels to be increased to enable the widening of the carriageway, resulting in some large reinforced soil slopes. Phi Group’s Textomur system was identified as a suitable solution with the company's expertise and experience also a key driver for its appointment.
Challenge
As with any large reinforced soil project, access to the working area for the delivery of materials is key so careful co-ordination with Principal Contractor Alun Griffiths (Contractors) Ltd was key.
There was also the added requirement to incorporate some large culverts through the face of the reinforced soil slopes, so how this interacted with both the face of the structure and the geogrid reinforcement needed to be carefully considered. This highlights the benefit of early engagement with a design-and-build specialist.
Solution
Two Textomur reinforced soil slopes were required:
Wall 1 - 67m-long, up to 9.6m max height, 555m2 face area
Wall 2 - 150m-long, up to 19m max height, 1,786m2 face area
The slopes were designed in-house by Phi Group, with geogrid lengths and strengths ascertained and the designs then adopted by Jacobs as part of the overall scheme design. Phi's experienced operatives on site had to contend with bad weather, and occasional restricted access to deliver materials such as the estimated 30,000m3 of granular fill material that was placed and compacted to form the reinforced soil mass.
The Textomur system involves the placement of prefabricated sacrificial steel mesh formwork to the face of the reinforced soil slope, a geotextile is placed to the inside face of the steel cage to enable a layer of topsoil growing medium. The geogrid soil reinforcement is then incorporated from the steel cage and extends back into the reinforced soil fill material.
The system has been widely used on a number of high-profile highways schemes but is also suitable for commercial and residential projects, especially where the re-use of site-won material is an option.








