Sector Housing, private
Project type Refurbishment
Services provided Site survey
Planning advice
Design
Product / system manufacture
Product / system supply
Year completed 2019
Project location West Midlands
Client Private premesis
Products used 75mm Geoweb & GeoJute 500
 
 

Challenge

In summer 2019, planning permission was granted for the construction of a steel frame storage shed at a private residence in Warwickshire. To lessen the impact of the new build on the surrounding area, the building was cut back into the slope of an adjacent field with the excavated soil used to form a new bund.

In order to minimise space taken from the field, the decision was taken to set the internal slope of the new bund at 45°. This then brought up the issue of how the soil and seed would be retained on the slope to allow for the desired vegetated finish. The client at this point contact Greenfix to seek advice on the best method for soil retention.

Solution

Following in-depth discussions between the client and the Greenfix Sales Team, it was agreed that the Geoweb® slope protection system would be the most suitable solution for this project.

The large cell 75mm Geoweb was selected due to the degree of slope and the desire to infill with topsoil and grass seed. The Client said: “the decision was made to purchase the Geoweb system, which was easy to install and held the soil on the slope at the perfect depth ready for seeding.”

Following the installation of the Geoweb® another issue on site was identified. Due to the location of the site the slope was vulnerable to high winds which made retaining newly sown grass seed challenging. After speaking with Greenfix once more, the recommendation to install Greenfix GeoJute 500, 100% biodegradablejute erosion control blanket was made.

Outcome

Following installation, the grass was fully established within 5 weeks which exceeded the client’s expectations


Challenge

In summer 2019, planning permission was granted for the construction of a steel frame storage shed at a private residence in Warwickshire. To lessen the impact of the new build on the surrounding area, the building was cut back into the slope of an adjacent field with the excavated soil used to form a new bund.

In order to minimise space taken from the field, the decision was taken to set the internal slope of the new bund at 45°. This then brought up the issue of how the soil and seed would be retained on the slope to allow for the desired vegetated finish. The client at this point contact Greenfix to seek advice on the best method for soil retention.

Solution

Following in-depth discussions between the client and the Greenfix Sales Team, it was agreed that the Geoweb® slope protection system would be the most suitable solution for this project.

The large cell 75mm Geoweb was selected due to the degree of slope and the desire to infill with topsoil and grass seed. The Client said: “the decision was made to purchase the Geoweb system, which was easy to install and held the soil on the slope at the perfect depth ready for seeding.”

Following the installation of the Geoweb® another issue on site was identified. Due to the location of the site the slope was vulnerable to high winds which made retaining newly sown grass seed challenging. After speaking with Greenfix once more, the recommendation to install Greenfix GeoJute 500, 100% biodegradablejute erosion control blanket was made.

Outcome

Following installation, the grass was fully established within 5 weeks which exceeded the client’s expectations


 
 
 
Downloads
 
 
 
Enquire
 

Also by Greenfix Soil Stabilisation & Erosion Control

Greenfix Soil Stabilisation & Erosion Control address and contact details

Greenfix Soil Stabilisation & Erosion Control
Old Manor Farm Yard
Beckford Road
Ashton under Hill
Evesham
WR11 7SU
Tel: 01386881493
Fax: 01642 618525
View on map
 
Follow Greenfix Soil Stabilisation & Erosion Control
 
Not found what you're looking for? View other options