Two retaining walls were required as a boundary for a new Multi Use Games Area (MUGA) being constructed at the University of St Mark & St John in Plymouth.

Slope-Loc in Flint colour was selected for the job.

Once the site information had been obtained it was sent to Anderton's Engineers, PaSCoE, who then carried out a design for the 35m2 of walls.

The height of the new walls and ground conditions meant that a combination of gravity and concrete backed solutions were applicable, thus negating the need for any additional excavation into the ground behind the proposed walls.