We have been helping designers and specifiers find the best solutions for their projects since 1988. EXTERNAL WORKS is an ESI.info brand.
Cycling infrastructure earns BREEAM Outstanding rating, London
Overview The refurbishment of 90 Long Acre, London, presented Cycle-Works with a challenge: how to install parking for a large number of bikes within an existing structure with limited space/ The solution contributed to the project achieving a BREEAM Outstanding rating - the highest level of recognition. The Challenge Because the work was carried
Click for full image
Gas-assisted 2-tier racks, vertical wall racks and Rounded A racks provided a space saving cycle parking solution
The refurbishment of 90 Long Acre, London, presented Cycle-Works with a challenge: how to install parking for a large number of bikes within an existing structure with limited space/ The solution contributed to the project achieving a BREEAM Outstanding rating - the highest level of recognition.
The Challenge
Because the work was carried out on an existing building Cycle-Works had to work within the constraints of the existing space to accommodate parking for 365 bicycles - a volume that required a mix of products and configurations.
The Solution
Cycle-Works used a combination of three rack types: gas-assisted Josta 2-tier racks, vertical wall racks (fitted both on frames and mounted directly to the walls), and Rounded A racks. The team were able to make use of wall space, floor space, and vertical height, creating space for the full 365-bike capacity without compromising accessibility.
The Outcome
The cycling infrastructure at 90 Long Acre contributed to the building's BREEAM Outstanding rating, recognising the project's broader commitment to sustainability.