Overview
  • FP McCann’s back-bolted segmental shaft rings have been used to build a 20.0m id storm overflow holding tank
  • To complete the shaft build, a central column consisting of FP McCann 3600mm diameter caisson rings has been constructed
  • Segmental shafts during installation
  • The 20.0m id shaft has been sunk 14.0 metres deep using the jacked caisson method of construction
  • Shaft segments are all factory fitted with EPDM rubber gaskets which provide an immediate water-tight seal
  • FP McCann’s back-bolted segmental shaft rings have been used to build a 20.0m id storm overflow holding tank

Interested in this product?

Select image for download

Select the images you'd like and we'll send you the best versions we have in a zip file with the supplier's website address, phone number and email address and a link to the source page

Select images

Select the images you'd like and we'll send you the best versions we have in a zip file with the supplier's website address, phone number and email address and a link to the source page

This site uses cookies to enhance user experience.