10m pedestrian bridge; 1 week from placing order to installation
Bison supplied a fully-assembled 10m-long pedestrian bridge to Cowran Estate Services, who had been contracted by the Highways department to re-route a water course near Morseby Hall, Cumbria. Access to build the bridge on site was challenging due to muddy ground conditions. Bison supplied a fully pre-assembled, long-life steel structure
Click for full image
10m pedestrian bridge; 1 week from placing order to installation
Bison supplied a fully-assembled 10m-long pedestrian bridge to Cowran Estate Services, who had been contracted by the Highways department to re-route a water course near Morseby Hall, Cumbria.
Access to build the bridge on site was challenging due to muddy ground conditions.
Requirement
Bison supplied a fully pre-assembled, long-life steel structure pedestrian bridge, within 1 week of the order being placed.
Cowran Estates craned the bridge directly onto the concrete abutments.