Context

Pop Up Power Supplies® supplied 9 retractable service power units to Chelsea Football Club.

Stadium designers worked with the owners to specify an outdoor power supply which could power the specialist UV lighting equipment to promote the condition of the pitch at Stamford Bridge.

Products supplied

Retractable telescopic feeder pillars from Pop Up Power Supplies® were specified for installation within the stadium arena, which provided a secure, silent and efficient power supply for the UV lighting equipment.

Outcome

Installed by Springfield Engineers over a 6-week timeframe, the Chelsea ground staff now have access to multiple 63A three-phase IP67 sockets, all with RCBO protection.

The beauty of the pop up power units is that when they are not in use they are simply lowered back into the ground, and a section of turf is laid over the lid to give a seamless appearance to the pitch area.