Context

Althon supplied 10 precast concrete headwalls for the A4119 dualling scheme at Radyr in Wales.

Project detail

All of the headwalls required factory-fitted accessories such a Kee Klamp handrail, gratings and aluminium stop logs. Having the accessories factory-fitted saves time on installation and has health and safety benefits.

The construction phase of this major scheme - to be delivered by Alun Griffiths (Contractors) Ltd - is funded with £11.4m from the UK Government’s Levelling Up Fund, in addition to funding previously committed by the Council and Welsh Government.